5 decisions waiting on someone

Ranked by impact, how long they have waited and what is stopped behind them.

Waiting
5
Critical impact
3
Past their deadline
0
Work items stopped
9
Median decision takes 6 days

Everything waiting

  • Critical impactDue in 3 days· waiting 5 days

    How to close the two outstanding artist assignments

    AI Cultural Short Film Program
    ABAnthony Bui decides

    Why this matters

    Critical impact — 2 work items cannot proceed, 2 milestones depend on it and 2 outcomes are affected.

    If it keeps waiting

    Contributor rights pack complete and Distribution conversations opened slip by however long this waits.

    What is waiting on it

    1. How to close the two outstanding artist assignments
    2. Obtain assignment agreements from 2 remaining artists
    3. Shortlist distribution and licensing routes
    4. Contributor rights pack complete
    5. Distribution conversations opened
    6. A production method the group owns and can license

    2 work items2 milestones1 launch-blocking deliverable

    Earliest milestone affected: Contributor rights pack complete (3 Sept)

    3 options · a recommendation is prepared
  • Critical impactDue Tomorrow· waiting 6 days

    Execute or renegotiate the supplier master agreement

    Regional Supply Chain Programme
    ABAnthony Bui decides

    Why this matters

    Critical impact — 2 work items cannot proceed, 2 milestones depend on it and 1 outcome are affected.

    If it keeps waiting

    Master agreement executed and Transition complete slip by however long this waits.

    What is waiting on it

    1. Execute or renegotiate the supplier master agreement
    2. Supplier master agreement — owner approval
    3. Transition plan for tier-2 suppliers
    4. Master agreement executed
    5. Transition complete
    6. 12% reduction in landed cost

    2 work items2 milestones2 launch-blocking deliverables

    Earliest milestone affected: Master agreement executed (2 Sept)

    3 options · a recommendation is prepared
  • Critical impactDue Today· waiting 4 days

    Approve the varied production scope

    Technology Expo Sydney
    ABAnthony Bui decides

    Why this matters

    Critical impact — 2 work items cannot proceed, 1 milestone depend on it and 2 outcomes are affected.

    If it keeps waiting

    Production build complete slip by however long this waits.

    What is waiting on it

    1. Approve the varied production scope
    2. Sign production supplier master agreement
    3. Finalise run of show with venue operations
    4. Production build complete
    5. Qualified export pipeline created for exhibitors

    2 work items1 milestone2 launch-blocking deliverables

    Earliest milestone affected: Production build complete (8 Oct)

    3 options · a recommendation is prepared
  • High impactDue in 2 days· waiting 3 days

    Approve the EVENT5D public experience for launch

    Technology Expo Sydney
    KAKenji Arai decides

    Why this matters

    High impact — 2 work items cannot proceed, 1 milestone depend on it and 1 outcome are affected.

    If it keeps waiting

    Public launch campaign live slip by however long this waits.

    What is waiting on it

    1. Approve the EVENT5D public experience for launch
    2. Approve EVENT5D public experience draft
    3. Brief media partners on launch campaign
    4. Public launch campaign live
    5. The 2026 edition covers its own cost

    2 work items1 milestone1 launch-blocking deliverable

    Earliest milestone affected: Public launch campaign live (5 Sept)

    2 options · a recommendation is prepared
  • High impactDue in 5 days· waiting 2 days

    Ship general availability with the billing defect open, or hold

    SaaS Product Launch
    SWSarah Whitlock decides

    Why this matters

    High impact — 1 work item cannot proceed, 1 milestone depend on it and 1 outcome are affected.

    If it keeps waiting

    General availability slip by however long this waits.

    What is waiting on it

    1. Ship general availability with the billing defect open, or hold
    2. Billing reconciliation defect — invoice rounding
    3. General availability
    4. General availability shipped with an SLA the team can hold

    1 work item1 milestone1 launch-blocking deliverable

    Earliest milestone affected: General availability (4 Oct)

    2 options · a recommendation is prepared