Technology Expo Sydney
Two-day trade expo bringing Australian deep-tech, advanced manufacturing and AI companies together with regional buyers at ICC Sydney.
- Mai Nguyen
- 16 Oct 2026 · in 5 weeks
- AU$388K of AU$780K
- 3/7 milestones
- 5 people
Project Truth
53 / 100
- 11
- 2
- +6.8
- 1
Raised schedule risk — Public launch campaign live — Project Doctor, 3 days ago
Approve the varied production scope
Go there- 20 tasks, last changed 2 days ago.
- 4 decisions, last changed 3 days ago.
- 5 deliverables, last changed 2 days ago.
- 2 outcomes, last changed 4 days ago.
- 8 gates, last changed 3 days ago.
- 57 recorded events, last changed today.
- Entered manually. Last touched 1 day ago. No finance system is connected.
- 5 items, last changed 8 days ago.
- 3 suppliers recorded from what was entered here. Nothing has been confirmed with the suppliers themselves.
Activity is not readiness
56
35
36
27
62
11 of 20 tasks
1 of 5 deliverables accepted
0 of 2 on track
What is blocked (11)
Production build (stage, rigging, AV)
Buyer matching programme
Public launch campaign
Approve the varied production scope
Approve the EVENT5D public experience for launch
Sign production supplier master agreement
Sign production supplier master agreement
Approve EVENT5D public experience draft
Production gate
Operations gate
Speakers gate
What will go wrong
Sign production supplier master agreement has been blocked for 6 days
- — Blocked since 2 Sept
- — On the critical path, so nothing behind it can start
- — Waiting on an approval
Every day blocked is a day added to the delivery date.
Likely delay 6–8 days
How that figure was arrived at
- 1.Get the approval, or remove the approval requirement if it is not warranted
- 2.Start downstream work that does not strictly need this finished
Approve the varied production scope has been waiting 4 days
- — Critical impact
- — 2 work items cannot proceed without it
1 milestone depend on it.
Likely delay 4–7 days
How that figure was arrived at
- 1.A recommendation is prepared — review it and decide
- 2.If it cannot be decided this week, say so explicitly and reschedule the work behind it
Tom Ferreira holds 2 of 2 critical-path items
- — 100% of the remaining critical path sits with one person
- — 9 items are open across the project
If that person is unavailable, the critical path stops entirely. There is no parallel route.
- 1.Move at least one critical-path item to another owner
- 2.Agree cover for that person before the next delivery increment
Acceptance window is tight on 3 launch-blocking deliverables
- — 9 acceptance criteria are still unmet across launch-blocking deliverables
- — The earliest is already 3 days past its date
Deliverables get accepted under time pressure, or the launch moves.
Likely delay 9–13 days
How that figure was arrived at
- 1.Review acceptance criteria and drop any that are not genuinely required for launch
- 2.Start acceptance on the criteria that can be met now rather than at the end
Delivery date at risk by 1–10 days
- — About 67 hours of work remain against roughly 12 hours a week of recent throughput
- — 1 item is blocked, the longest for 6 days
- — 2 unmade decisions of high or critical impact
- — 1 milestone is already past due
Target date is 38 days away. 4 milestones remain.
Likely delay 1–10 days
How that figure was arrived at
- 1.Clear the 2 decisions waiting — they cost nothing to make and are holding work
- 2.Unblock or reassign the 1 stopped item
- 3.Freeze non-critical scope so remaining throughput goes to the critical path
Approve the EVENT5D public experience for launch has been waiting 3 days
- — High impact
- — 2 work items cannot proceed without it
1 milestone depend on it.
Likely delay 3–6 days
How that figure was arrived at
- 1.A recommendation is prepared — review it and decide
- 2.If it cannot be decided this week, say so explicitly and reschedule the work behind it
What readiness gate is preventing delivery
Production
Production is blocked — Supplier master agreement is unsigned, so the build cannot be scheduled. Nothing ships until it clears. Mai Nguyen owns it.
What actual execution history shows
5 items completed in the last 28 days, about 12 hours a week.
- 12h
- 8.2
- 6.1
- —
Slowing
2 of 2 items moved
How health was calculated
- One person holds 100% of open critical-path work
- Production gate is not cleared, with 11 open blockers in total
- 2 decisions waiting, the oldest for 4 days
- 1 of 2 critical-path items are blocked
- 27% outcome readiness at 72% of elapsed time
- 35% of outputs ready at 72% of elapsed time
- 2 awaiting approval
- 1 blocked, the longest for 6 days — 6.1 days lost to blocking in the last 28
- About 5.6 weeks of work against 5.4 weeks remaining, at measured throughput
Decisions waiting
Open queue- Approve the varied production scope
- Approve the EVENT5D public experience for launch
Are we moving toward the outcome?
- 150 qualified buyer introductions logged and attributed
- Not measured yet
- Buyer matching programme
- Exhibitor floor plan
- Post-event attribution report
- AU$400K sponsorship committed against AU$780K planned cost
- AU$140K committed, AU$85K in proposal
- Production build (stage, rigging, AV)
- Public launch campaign
Qualified export pipeline created for exhibitors
42%
The 2026 edition covers its own cost
25%